# UpStation design UPS-DSN-20261103-BKCU — Budgetary design and estimate — not a quote

Prepared 2026-11-03 for **Example SaaS Co** · — · prices as of 2026-11-03

## 4× 8-GPU RTX PRO 6000 inference farm (32 GPUs), Texas colo

4× 8x NVIDIA RTX PRO 6000 Blackwell Server Edition (32 GPUs, PCIe class). Networks: front end 25G on 2 switches; oob 1G on 1 switch. 1 rack at ≤ 40 kW, 34.33 kW provisioned, in Texas colo. Every figure is computed from the ai.upstation.io catalog with the arithmetic shown below.

| Hardware (CapEx) | Colocation | Year one | 3-year total | 5-year total |
|---|---|---|---|---|
| $724,604.56 | $7,724.00/mo (34.33 kW) | $817,292.56 | $1,002,668.56 | $1,188,044.56 |

**Delivery:** 5 weeks, set by 8x NVIDIA RTX PRO 6000 Blackwell Server Edition, Intel — SYS-422GA-NRT. **Colo:** Texas at $225/kW/month × 34.33 kW, 36-month term.

## Requirements

| Requirement | Value |
|---|---|
| Workload | inference |
| GPUs | 32 |
| Rack limit | 40 kW |
| Colo | Texas |
| Timeline | within 6 weeks |

## How it was designed

- GPUs → nodes: ceil(32 ÷ 8) = 4 × 8x NVIDIA RTX PRO 6000 Blackwell Server Edition, Intel (32 GPUs; nodes ship fully populated).
- Class: PCIe — each GPU works alone (inference). Does the model at its precision fit one GPU's memory, and can each GPU work alone? Yes: PCIe. No: HGX. Distributed training is never served by PCIe servers.
- Front-end: 2 ports per host, one to each switch of an MLAG pair of 48× 25G + 8× 100G switches; 4 ports per switch of 48 usable → 1 pair(s).
- OOB: 4 hosts + 2 switches = 6 × 1G ports → 1 × 48× 1G RJ45 + 4× 10G.
- GPU nodes per 40 kW rack = min(floor(40 U ÷ 4 U), floor(40 ÷ 8.47 kW)) = 4 (power binds).
- Compute 1: 19 U, 34.33 kW provisioned → 1 × 415V 3-ph 60A circuit pair (A+B), 80% of each feed; 19 power cords per feed.

## Network topology

```mermaid
flowchart TB
  FE["Front-end MLAG pair: 2× 48× 25G + 8× 100G<br/>25G, storage converged"]
  GN -- "2× 25G per node" --> FE
  FE -. "uplinks to your core (not priced)" .-> CORE(("Your network"))
  OOB["OOB: 1× 1G switch"] -. "BMC, 6 ports" .- GN
```

## Racks and power

(rack elevation: the SVG drawing in the HTML/PDF version of this document)

| Rack | Space | Provisioned | Circuits | Devices |
|---|---|---|---|---|
| Compute 1 | 19/40 U | 34.33 kW | 1× 415V 3-ph 60A (A+B) | 4× 8x NVIDIA RTX PRO 6000 Blackwell Server Edition, 2× 48× 25G + 8× 100G switch — front-end pair, MLAG, 1× 48× 1G RJ45 + 4× 10G switch — OOB |

## Bill of materials

| Section | Item | Qty | Unit (USD) | Extended | Lead time | Source |
|---|---|---|---|---|---|---|
| GPU servers | 8x NVIDIA RTX PRO 6000 Blackwell Server Edition, Intel — SYS-422GA-NRT | 4 | $177,430.31 | $709,721.24 | In stock (barebone and RTX PRO 6000 cards, 2026-11-03); conf | https://ai.upstation.io/p/UPS-GPU-RTXPRO-8 |
| Front-end network | 48× 25G + 8× 100G switch (front-end pair, MLAG) — FS S5470-48Y, PicOS | 2 | $6,049.00 | $12,098.00 | 97 in stock (global warehouse, 2026-11-03). ~1 week | https://ai.upstation.io/p/UPS-NET-25G-48 |
| Front-end network | +1x 25G 2x SFP28 CX6 NIC (AOC-631102AN-ADAT) (listed option, one per GPU node) | 4 | $344.08 | $1,376.32 |  | https://ai.upstation.io/p/UPS-GPU-RTXPRO-8 |
| Front-end network cabling | 25G 2 m passive DAC — GPU nodes to the pair, 2 per node | 8 | $39.00 | $312.00 |  | https://ai.upstation.io/switches |
| Front-end network cabling | 100G 2 m passive DAC — peer link | 2 | $54.00 | $108.00 |  | https://ai.upstation.io/switches |
| Out-of-band | 48× 1G RJ45 + 4× 10G switch (OOB) — FS S3410-48TS, PicOS | 1 | $989.00 | $989.00 | 593 in stock (global warehouse, 2026-11-03). ~1 week | https://ai.upstation.io/p/UPS-NET-1G-48 |
| | **Hardware total** | | | **$724,604.56** | | |

## Assumptions

- GPU server: 8x NVIDIA RTX PRO 6000 Blackwell Server Edition, Intel (UPS-GPU-RTXPRO-8), the default PCIe line (proposed)

## Not included

- Racks, PDUs, whips and cabling labour
- Uplinks to the buyer's core network
- Software (cluster manager, storage software), unless listed
- Taxes, shipping and duties
- Installation and on-site services

**Next step.** Book the intro (https://calendly.com/alecglover/intro-call) or email alec@upstation.io with the design ID; UpStation validates the design and introduces the supplier that fits.

Prepared by UpStation from public supplier prices at ai.upstation.io. Budgetary only; the supplier confirms price, availability and lead time on order. UpStation does not resell. alec@upstation.io