# UpStation rack plan UPS-DSN-20261103-BKCU — budgetary design, not a quote

Prepared 2026-11-03 for **Example SaaS Co** · — · prices as of 2026-11-03

## 4× 8-GPU RTX PRO 6000 inference farm (32 GPUs), Texas colo

**34.33 kW provisioned** (nameplate ÷ 0.8), each rack held to 40 kW, A+B feeds (either one carries the whole rack).

(rack elevation: the SVG drawing in the HTML/PDF version of this document)

## Power per rack

| Rack | Space | Provisioned | Circuits (A+B) | Load per feed | Cords per feed |
|---|---|---|---|---|---|
| Compute 1 | 19/40 U | 34.33 kW | 1× 415V 3-ph 60A | 80% | 19 |

## Colocation by location

| Location | $/kW/month | Per month | Term total | Sales tax | Property tax |
|---|---|---|---|---|---|
| Montana | $260 | $8,926.00 | $321,336.00 (36 mo) | none | none on the first $1M of equipment, about 0.8%/yr above |
| Texas (this design) | $225 | $7,724.00 | $278,064.00 (36 mo) | 8.25% (6.25% state + local); the data-center exemption needs $200M and 20 jobs | about 2.2%/yr of market value |
| Oregon | $175 | $6,008.00 | $216,288.00 (36 mo) | none | about 1.5-2%/yr of market value (ORS 308.290); abatements closed to data-center property since 2026 |
| Pennsylvania | $250 | $8,582.00 | $308,952.00 (36 mo) | 6% (8% Philadelphia, 7% Allegheny), or none if the facility is state-certified and the tenant holds its own exemption certificate (100 kW+, 2-year contract) before buying | none |
| Canada (Ontario, Quebec) | $225 | $7,724.00 | $278,064.00 (36 mo) | HST 13% (Ontario) or GST+QST (Quebec) on hardware and colo, recovered as an input tax credit by a registered business | none |

## How it was laid out

- GPU nodes per 40 kW rack = min(floor(40 U ÷ 4 U), floor(40 ÷ 8.47 kW)) = 4 (power binds).
- Compute 1: 19 U, 34.33 kW provisioned → 1 × 415V 3-ph 60A circuit pair (A+B), 80% of each feed; 19 power cords per feed.

## Devices

| Rack | U | Name | Device | RU | kW | PSUs |
|---|---|---|---|---|---|---|
| Compute 1 | 40 | fe-1a | 48× 25G + 8× 100G switch — front-end pair, MLAG | 1 | 0.19 | 2 |
| Compute 1 | 39 | fe-1b | 48× 25G + 8× 100G switch — front-end pair, MLAG | 1 | 0.19 | 2 |
| Compute 1 | 38 | oob-1 | 48× 1G RJ45 + 4× 10G switch — OOB | 1 | 0.07 | 2 |
| Compute 1 | 13 | gpu-04 | 8x NVIDIA RTX PRO 6000 Blackwell Server Edition | 4 | 8.47 | 8 |
| Compute 1 | 9 | gpu-03 | 8x NVIDIA RTX PRO 6000 Blackwell Server Edition | 4 | 8.47 | 8 |
| Compute 1 | 5 | gpu-02 | 8x NVIDIA RTX PRO 6000 Blackwell Server Edition | 4 | 8.47 | 8 |
| Compute 1 | 1 | gpu-01 | 8x NVIDIA RTX PRO 6000 Blackwell Server Edition | 4 | 8.47 | 8 |

## Assumptions

- GPU server: 8x NVIDIA RTX PRO 6000 Blackwell Server Edition, Intel (UPS-GPU-RTXPRO-8), the default PCIe line (proposed)

**Next step.** Book the intro (https://calendly.com/alecglover/intro-call) or email alec@upstation.io with the design ID; UpStation validates the design and introduces the supplier that fits.