Prices in USD as of 2026-09-09; final price confirmed on order. Continental US; Canada quoted case by case. Orders and quotes: book a meeting. Every page: llms.txt (map) · homepage (all tables) · catalog.json (data).

UpStation sizes a deployment in this order: GPUs → nodes → networks → storage → racks and power → bill of materials. The rules below are planning conventions (the same data is in catalog.json under sizing); figures marked estimate are not vendor specifications. Two worked designs computed with these rules are listed under Reference builds.

Before sizing, settle

GPUs to nodes

Networks

PlaneCarriesPorts per nodeOversubscription
GPU fabricCollectives only (all-reduce, GPUDirect RDMA); never storage1 port per GPU at the GPU generation's speed: H200 400G (listed option, 8× 400G), B300 800G (on board, 8× 800G). None on PCIe GPU servers unless the buyer asks1:1 non-blocking
Front-end (converged)Client access, orchestration, in-band management, and storage unless a storage plane is dedicated2 ports per node, one to each switch of a pair (25G floor; 100G or 200G when the base build or option provides it)3:1 (storage-facing 4:3 or better)
Storage (dedicated)Parallel file system or NAS data path at scale2 ports per storage node and per GPU node on the storage plane, only when that plane is dedicated (see 'Dedicated storage plane when'); otherwise storage rides the front-end plane1:1
OOBBMC and switch management1× 1G BMC port per node plus 1× 1G management port per switch, on a 48× 1G switch (1 per rack or per 48 ports)n/a

Storage

ProtectionEfficiency (usable ÷ raw before fill ceiling)
Replica 30.333
EC 2+20.5
EC 4+20.667
EC 8+20.8
EC 8+30.727
EC 8+40.667
RAID 6 10+20.833
RAID 6 8+20.8
RAID 6 6+20.75
RAID 100.5
Storage nodeRaw TBPortsLine rate GB/sPlanning GB/s per nodeRAID 6 10+2 plannable TB per nodeNote
2U all-NVMe storage node, dual socket, 24x 7.68TB NVMe (184TB raw)1842× 100G (4 with the listed option)2520130.3line rate 2 × 100 Gb/s ÷ 8 = 25 GB/s; plan 20 GB/s per node (estimate, software dependent); 50 GB/s line rate with 4× 100G
2U HDD storage node, single socket, 24x 24TB SAS (576TB raw)5762× 100G255407.824 nearline drives at about 250 MB/s each ≈ 6 GB/s streaming (estimate); plan 5 GB/s; add NVMe DB/WAL (1–4% of HDD capacity) via the rate card for Ceph

Racks, power and management

GPU serverRUProvisioned kWPer 40 kW rackRack kWBinds on
8x NVIDIA B300 (HGX B300 NVL8), Intel816.96233.92power
8x NVIDIA H200 (HGX H200), Intel811.34334.02power
8x NVIDIA RTX PRO 6000 Blackwell Server Edition, Intel48.47433.88power
8x NVIDIA RTX PRO 6000 Blackwell Server Edition, AMD48.37433.48power
8x NVIDIA RTX 5090 (passive server edition), AMD47.99539.95power
8-GPU host, Tier 1 (Supermicro), PCIe 5.0, Intel Xeon 6 (TDX)41.381013.8space
8-GPU host, Tier 1 (Supermicro), PCIe 5.0, Intel 5th Gen Xeon (TDX)52.19817.52space
8-GPU host, Tier 1 (Supermicro), PCIe 5.0, AMD51.25810.0space
8-GPU host, Tier 2 (Octoserver), PCIe 5.0, AMD41.311013.1space
8-GPU host, Tier 2 (Octoserver), PCIe 4.0 budget, AMD41.341013.4space